Quail Hollow No. 2

Updates:

** This project is complete **

November 8, 2021: The contractor has completed all localized concrete repairs, clean up and re-sodding in this neighborhood. There is some minor clean-up, sod and irrigation repair left to complete before the project can be closed out.

August 30, 2021: The contractor is almost finished in this neighborhood including cleanup and landscape repair. There is some minor concrete work, including clean-up, sod and irrigation repair left to complete before the project can be closed out.

April 2, 2021: The contractor is continuing work on Hollow Bend and has started work on Whitewing and Harvester.

March 8, 2021: The contractor as finished pavement repair on Retriever Lane and has completed half of the pavement on Hollow Bend.

February 12, 2021: In order to avoid the holidays, the contractor delayed starting on the project until January 4, 2021. Repairs in Quail Hollow No. 2 Subdivision are progressing nicely. The contractor is working on Hollow Bend right now.

December 3, 2020: The contractor is expected to begin construction on December 14, 2020.

Project Description:

RealTexasRoads LogoThis page is dedicated to street repairs in the Quail Hollow No. 2 subdivision. Repairs in this neighborhood are funded through the Real. Texas. Roads. program and covers repairs on the following streets:

STREET NAME FROM TO
BRUSHWOOD TRIPP HOLLOWBEND
BRUSHWOOD LN CRUSHWOOD CULDESAC
HARVESTER HOLLOWBEND BRUSHWOOD
HOLLOWBEND TRIPP QUAIL HOLLOW
QUAIL HOLLOW AMERICANA POTEET
RETRIEVER HOLLOWBEND BRUSHWOOD
WHITEWING HOLLOWBEND BRUSHWOOD

Quail Hollow No. 2

Quail Hollow No. 2

Expected Construction Process - Localized Full Depth Concrete Repair:

City staff will determine what areas of the street and sidewalk are in moderate to severe condition and the concrete at those locations will be removed and new reinforced concrete will be poured at those locations. This will not replace entire streets, but will rather replace only the moderate to severe locations of pavement failure. The concrete identified for replacement will vary in size and length. After the concrete is removed and replaced, the contractor will grade, place sod and clean up the area disturbed by the construction.


Real. Texas. Roads. is the program name for the road repairs funded by the $125 million bond sale approved by voters in November 2015. Repairs under this program are limited to residential, 2-lane roadways. Click here to see information on the entire program of road repairs.