LBJ Construction Project


GENERAL PROJECT INFORMATION.

The Texas Department of Transportation has selected McCarthy Building Company, Inc. for award of a $46 million contract to construct Phase 2 of the Mesquite Section of the LBJ Project. McCarthy Building Company, Inc. has established their field offices along the eastbound IH 30 frontage road just west of N. Galloway Avenue. The project will start in January 2006 and is expected to take two years to complete. Major features of this project include:

  • Rebuilding and widening IH 635 bridge over Town East Boulevard to 12 lanes
  • Adding a south IH 635 to north IH 635 U-turn lane beneath the new bridge
  • Creating dual-left turn lanes at IH 635, lowering and realigning Town East Boulevard from Towne Crossing Boulevard to West Emporium Circle
  • Adding a new northbound entrance ramp from Towne Centre Drive to IH 635
  • Modifying the north and southbound Town East Boulevard entrance and exit ramps
  • Reconstructing main-lane pavement from Town East Boulevard to just north of US 80
  • Constructing a new southbound IH 635 frontage road from eastbound IH 30 to Town East Boulevard
  • Relocating underground natural gas, electric, water, sanitary sewer, and storm sewer lines
  • Enhanced landscaping at the IH 635 overpass across Town East Boulevard
  • Constructing a new sound wall along the northbound IH 635 frontage road between US 80 and Towne Centre Drive

The project’s construction phasing and comprehensive detour plan allow all businesses in the project area to remain open during construction. The overall project area is indicated on the map. Dynamic message signs advising motorists of detours and delays will be placed along all freeways and additional detour signage will be placed along city streets leading to the project area.

Questions on the project may emailed directly to the City Engineer, Matt Holzapfel, at mholzapf@ci.mesquite.tx.us .

 

CURRENT PROJECT INFORMATION

  • McCarthy is completing small punch out items such as small paving items, repairs to the Sears Parking Lot, removing construction barricading and signage, removal of erosion control, general cleanup and fine grading, etc..

  • McCarthy is also working on cleaning up their staging areas, temporary batch plant site and job site trailer areas.

  • McCarthy has completed the painting of the sound-wall south of Towne Centre Drive adjacent to the apartments. They still grading the areas adjacent to the sound-wall and removing stockpiled soil from the south end of the soundwall.

  • Irrigation is almost complete. The landscaper has completed much of the landscaping installation even though the irrigation system is not working due to lack of electrical power. They will water the newly planted landscaping by hand until the irrigation system is activated. Accent lighting for the planting beds is complete. Electrical meter for irrigation should be set next week.

  • Pavement removal and replacement from Emporium East to Belt Line Road on Town East Blvd. is not part of the TXDOT project. This work is on a City Capital Project

  • Project is substantially complete and it is anticipated for total completion mid-September 2009.

  • Shane Harp is the TXDOT project manager.

Here are photographs of construction activity for this week.

Additional information can be found on TxDOT's web site.